French energy company ENGIE, along with its partners Orascom Construction and Aeolus, has achieved financial close for the 900 MW Gulf of Suez 3 wind farm in Egypt, clearing the way for full-scale construction of the project.
Located near Ras Shokeir in Egypt’s Gulf of Suez region, the project is expected to become ENGIE’s largest onshore wind farm globally.
It will be developed, owned and operated by Shokeir Wind Energy, a joint venture in which ENGIE holds a 35 per cent stake, Orascom Construction holds 25 per cent and Aeolus owns the remaining 40 per cent.
The project will be connected to the electricity grid in three phases. The first 300 MW phase is expected to enter commissioning in January 2028, while the entire 900 MW facility is scheduled to achieve commercial operation in the third quarter of 2028.
The project has secured non-recourse financing from a consortium of international financial institutions and banks, including Japan Bank for International Cooperation (JBIC), PROPARCO, FMO, Société Générale, Crédit Agricole Corporate and Investment Bank, and KfW IPEX-Bank. Its electricity sales are backed by a 25-year Power Purchase Agreement (PPA) with the Egyptian Electricity Transmission Company.
Under the project arrangement, Orascom Construction will undertake civil and electrical works, while Goldwind will supply, install and commission the wind turbines.
Once operational, the wind farm is expected to generate approximately 4 TWh of renewable electricity annually.
It will contribute to diversifying Egypt’s electricity mix, meeting rising demand for low-carbon power and strengthening the country’s energy security.
Gulf of Suez 3 will be ENGIE’s third wind energy project in Egypt, following the 262.5 MW Ras Ghareb wind farm and the 650 MW Red Sea Wind Energy project. Together, the three developments will represent close to 2 GW of wind power capacity in the country.