Exide Industries Ltd has reduced its shareholding in Ulric Renewables Private Limited from 39.08 per cent to 26.07 per cent after a 10.5 MW captive wind power project in Maharashtra failed to achieve commissioning within its scheduled timeline. The company disclosed the development in a regulatory filing submitted to the stock exchanges on November 18, 2026.
Ulric Renewables is a special purpose vehicle (SPV) promoted and incorporated by Cleantech Solar India OA 2 Pte. Ltd. to develop captive wind power projects with a combined contracted capacity of 18.9 MW. These projects were planned to supply renewable electricity to Exide Industries’ manufacturing facilities in Maharashtra and Tamil Nadu.
According to the company’s filing, the 10.5 MW wind power project at Jath in Maharashtra, intended to supply electricity to its Maharashtra factories, could not be commissioned within the scheduled commencement date.
Following this development, Exide, Ulric Renewables and Cleantech Solar India OA 2 Pte. Ltd. mutually agreed to revise their existing arrangements. The change was formalised through amendment and settlement documents executed by the parties, resulting in a reduction in Exide’s equity holding in the renewable energy venture.
However, the company’s existing renewable power arrangement in Tamil Nadu remains unaffected. The 8.4 MW captive wind power project supplying electricity to Exide’s Hosur facility continues to operate under the existing arrangement. Ulric Renewables will continue supplying power to the facility through this project.
The two wind power projects were originally planned as part of Exide’s efforts to source renewable electricity for its manufacturing operations.
While the Hosur project continues to provide renewable power, the delay in the Maharashtra project has led to a revision in the company’s equity participation in Ulric Renewables.
Exide’s latest disclosure updates its earlier communication to the stock exchanges dated April 10, 2023, when the company reported an equity investment of 39.08 per cent in Ulric Renewables.
The original arrangement covered the development of 18.9 MW of captive wind power capacity across the two states.
The company has not disclosed the financial consideration, if any, associated with the revised shareholding arrangement. It has also not specified the reason for the delay in commissioning the Jath project or provided a revised commissioning schedule.
The development highlights the execution challenges that can affect captive renewable energy projects, particularly when industrial power consumers depend on project timelines to meet their renewable electricity requirements.
For Exide, the 8.4 MW wind power supply arrangement for its Hosur facility remains operational, while the planned 10.5 MW capacity for its Maharashtra factories has not achieved commissioning within the original schedule.